Red Metal's Chilean Ore Delivery Beats Schedule by Four Months

Image
Red Metal's Chilean Ore Delivery Beats Schedule by Four Months

Vancouver, BC – September 08, 2026 -- Red Metal Resources Ltd. (CSE: RMES) (OTCPINK: RMESF) (FSE: I660) has completed its first copper sulphide ore deliveries to Empresa Nacional de Minería's (ENAMI) Vallenar processing plant, roughly four months ahead of the seven-month development timeline set out in its mining lease.

KMT delivers 591.66 tonnes of copper ore in 16 truckloads

Lessee and operator Minera KMT SpA hauled the stockpiled ore from Level 7 of the north tunnel at the Farellon 1/8 concession to ENAMI on August 20th and 21st, 2026. The delivery, weighing approximately 591.66 tonnes net, followed the May 14th, 2026, mining lease and royalty agreement between Red Metal and KMT, arriving within roughly three months rather than the projected seven.