Zetwerk Installs US Transformer, Cuts Lead Times to 12-15 Months

Image
Zetwerk Installs US Transformer, Cuts Lead Times to 12-15 Months

BENGALURU – October 29, 2026 -- Zetwerk Manufacturing Businesses Ltd. says it can deliver power transformers in the US within 12 to 15 months, against industry averages of 36 to 42 months, after completing the installation of a Zetwerk-manufactured unit in North Carolina with its US subsidiary Unimacts.

Energy revenue rises 86.90% to ₹6,507.57 crore

Zetwerk's Energy vertical generated ₹6,507.57 crore (₹65,075.72 million) in FY26, up 86.90% year on year. It contributed 69.42% of the company's Manufacturing revenue. In FY2026 the company received power transformer orders worth ₹2,032.25 crore (₹20,322.52 million).