Lindian Lifts Kangankunde Ore Stockpile 19% to 149,000 Tonnes

Image
Lindian Lifts Kangankunde Ore Stockpile 19% to 149,000 Tonnes

Perth – October 15, 2026 -- Lindian Resources (ASX: LIN) increased ore stockpiles at its Kangankunde Rare Earths Project in Malawi to approximately 149,000 tonnes, up about 24,000 tonnes, or 19%, from September 2026, as the company holds to a December 2026 target for first monazite concentrate.

The stockpile tonnage is derived from the project's existing Ore Reserve estimates, according to the company.

Power infrastructure reaches key milestones ahead of November energisation

The 33kV overhead line has been commissioned to the transformer yard. Both 1,250 kVA plant transformers have returned to site after passing factory acceptance testing. Lindian is targeting site energisation in the first week of November 2026, which would leave roughly one month before the planned first production.