PJM asks FERC to halve data center grid study time to 12 months

Image
PJM asks FERC to halve data center grid study time to 12 months

UNITED STATES -- November 24, 2026 -- PJM Interconnection, the largest grid operator in the United States, has asked the Federal Energy Regulatory Commission (FERC) to cut the study period for connecting new large power consumers from two years to 12 months, a 50% reduction by our calculation. The proposal responds to a supply shortfall of about 6.8 GW, according to a Reuters report, as data center demand outpaces new generation.

PJM wants new-load studies cut by 12 months to find urgent grid upgrades

The filing covers two processes: commissioning of new generation capacity and connection of large consumers to the grid. PJM would shorten the connection study from 24 months to 12. The grid operator says faster processing would also let it identify the locations that need the most urgent grid upgrades for new data center connections.