Rupa Lake project in Nepal costs Rs 4.53 billion, 70% complete

Image
Rupa Lake project in Nepal costs Rs 4.53 billion, 70% complete

POKHARA -- November 19, 2026 -- Nepal's Rupa Lake redevelopment in Kaski district, valued at Rs 4.5288 billion, is about 70% complete. Forest-land and tree-removal issues have pushed the finish past the original fiscal 2024/25 target, and the remaining work is now expected to take about two more years.

The project is implemented through the Irrigation and Water Resources Management Project in Pokhara. It will enlarge the lake from about 122 hectares to about 183 hectares, an increase of 61 hectares, or 50%. By our calculation, the budget works out to roughly Rs 24.7 million per hectare of the planned final lake area. The project description does not break down the Rs 4.5288 billion by component.

A 635-metre dam drives the 50% expansion of Rupa Lake

The dam combines a 590-metre earthen embankment with a 45-metre concrete section. That makes 635 metres in total by our calculation, of which the embankment is about 93%. The structure is six metres high and reaches about 45 metres in width in some sections. A landscaped park is planned across its wider upper part.

An eight-kilometre road along the eastern shore is already built.

Visitor attractions include an island temple on pillars 12 metres below the surface

The planned temple in the middle of the lake draws its architecture from Tal Barahi Temple on Phewa Lake. It will stand on a platform supported by pillars extending about 12 metres below the water surface.

Other components are:

  • walking routes along the southern and western shores;
  • a cycling lane beside the forest on the western side;
  • a beach volleyball court.
Different shoreline limits could force four or five houses to relocate

The lake lies along the boundary between Pokhara Metropolitan City and Rupa Rural Municipality. The prescribed shoreline boundary is 100 metres in the city and 50 metres in the rural municipality. If the 50-metre limit is kept after the expansion, approximately four or five houses may require relocation. Efforts are under way to agree a more consistent approach.

Forest land and tree removal must also be resolved before some remaining infrastructure can proceed.

A cooperative with 1,154 shareholders earns Rs 14 million a year from the lake

A local cooperative active in lake restoration and commercial aquaculture has 1,154 shareholders. It recorded approximately Rs 14 million in annual revenue. The project budget is roughly 320 times that figure, and the revenue averages about Rs 12,100 per shareholder, by our calculation.

The project description says better access and recreation facilities could support accommodation, transport and tourism services around the lake. It adds that any benefit depends on completion of the project and on the extent of local participation.