Silvercorp Raises El Domo Budget to $298.2M, Delays Start to 2027

Image
Silvercorp Raises El Domo Budget to $298.2M, Delays Start to 2027

Vancouver – – November 04, 2026 -- Silvercorp Metals Inc. (TSX/NYSE American: SVM) raised the construction budget for its El Domo Project in Ecuador to $298.2 million, up $14.6 million from the $283.6 million estimate disclosed on February 4, 2026, and pushed its production target to November 2027 after a four-month delay.

The new figure compares with a $248 million budget in the 2021 Feasibility Study. The company attributes the schedule slip to extended rainfall linked to Super El Nino and says the date remains subject to weather and contractor performance.

Ecuador's diesel subsidy removal adds $8.3 million to remaining construction costs

Diesel rose from under $3 per gallon in December 2024 to $5.64 per gallon in October 2026, an increase of $2.70 per gallon, after Ecuador eliminated diesel subsidies. The fuel adjustment is $3.6 million for Package #1 and $4.7 million for Package #2.

The Package #2 mining contract, awarded to China Railway 19th Bureau Group Co., Ltd. (CRCC 19) on a unit-cost basis and valued at $35 million, rises by $5.0 million. Of that, $4.7 million reflects the diesel price increase.

Heavy rainfall, power infrastructure and plant contract refinements add further costs

Water-management upgrades add $4.7 million to the Package #1 tailings storage facility (TSF) budget: $3.5 million for enhanced designs and reinforcement, and $1.2 million for site cleaning. Two cofferdams and pipes beneath the TSF starter dam, plus cemented roadside ditches, add nearly $2 million.

Site power supply equipment rises by $2.4 million on detailed engineering. Two new Reactive Power Compensators are estimated at $2 million and other power items at $1.3 million, a combined $3.3 million. The Package #3 processing plant contract adds $3.7 million after refinement of quantities and unit rates.

Silvercorp offsets $9.8 million, including a $2.7 million contingency cut

Savings include $1.8 million from using rock from plant site preparation for haul road construction, $1.5 million from eliminating the West Non-contact Water Channel, and $0.7 million from a smaller permanent camp. The company also cut contingency by $2.7 million. That is a reduction in its allowance for future overruns rather than a direct saving, and $14.3 million of contingency remains.

Processing plant foundations advance while powerline approvals stall

Foundations were 92% complete for the fine ore bin, 45% for the grinding and flotation plant, 21% for the thickener, 86% for the dewatering plant, 75% for the warehouse and 35% for the oil depot. The lab building is 78% complete and the office 46%. Site preparation for the process plant is finished.

Actual expenditures at September 30, 2026 are not significant. Most costs sit in pre-fabricated structural steel that has been ordered and shipped, with payment pending arrival at the Ecuador port and final installation. Most equipment is ordered, with a roughly 30% down payment totaling about $10.6 million paid.

Powerline construction has been delayed by additional reviews and approvals required by CNEL, and only the El Domo substation has started. Ten gen-sets with 17 MW of capacity are manufactured and ready to ship as an independent power supply. Longer reliance on them could raise operating costs.