Star Gold files plan for 75 drill holes at Longstreet in Nevada

Image
Star Gold files plan for 75 drill holes at Longstreet in Nevada

COEUR D'ALENE, Idaho -- November 24, 2026 -- Star Gold Corp. (OTCQB: SRGZ) submitted a Plan of Operations on November 12, 2026 to the U.S. Forest Service for up to 75 exploration drill holes over three years at its Longstreet Gold Silver Project in Nevada. Only 38 of those holes, about 51%, are in Phase 1; the other 37 depend on Phase 1 results at two vein targets.

The Red Cyprus North Exploration Project plan went to the Humboldt Toiyabe National Forest, Austin Tonopah Ranger District. It covers drilling from existing roads, newly planned access roads and helicopter-supported sites.

Phase 1 puts 31 of its 38 holes on the Main and North areas

Phase 1 includes eight holes in the Main Pit area, reached from existing roads, and 23 holes in the North area, reached by newly planned roads. Together that is 31 of the 38 Phase 1 holes, or about 82%. The remaining seven holes are at Cyprus Ridge and Red Knob.

North lies directly north of Main across the access canyon. Main is the site of Star Gold's current mineral resource. The company says mineralization at North looks similar in structure and composition to Main.

Three earlier holes at North hit low-grade oxide gold mineralization near surface. They were drilled from existing disturbance and could not reach the primary target defined by surface mapping and sampling. The 23 planned holes are about eight times that earlier count. According to the company, they are meant to test the bulk of North in its most prospective areas.

Vein targets get seven holes before the Phase 2 decision

Cyprus Ridge and Red Knob show multiple events of banded epithermal quartz veins at surface. The company describes them as potential for a deeper, vein-hosted target.

If Phase 1 results there are encouraging, Phase 2 will build new roads for 19 more holes at Cyprus Ridge and 18 at Red Knob. By our calculation, the two targets account for 44 of the 75 holes, or about 59%. Only 7 of those 44, about 16%, are drilled before the Phase 2 decision. The company did not disclose the program's cost.

CEO Lindsay Gorrill says the plan keeps the company on schedule. Senior Geologist Richard Kern says it lets the company "drill where the geology points."

Core drilling covers 57 of the 75 planned holes

Star Gold plans solid core drilling (HQ core with some PC casing) at 57 holes, about 76% of the total. It plans reverse circulation air rotary drilling at the other 18. Either method can be used depending on site conditions, and one hole will be drilled at each site.

Planned depths range from 500 to 2,080 feet and average about 960 feet. At that average, 75 holes would total roughly 72,000 feet of drilling by our calculation.