Project Milestone

Recurrent Energy Starts Operation of 200 MWp Villameca Solar Plant

Kitchener – – October 15, 2026 -- Recurrent Energy, a subsidiary of Canadian Solar (NASDAQ: CSIQ), has started commercial operations at its 200 MWp Villameca solar project in Castilla y León, Spain, bringing the company close to 1 GW of operating solar capacity in the country by the end of the year.

Villameca is expected to generate 359,172 MWh of electricity a year

The photovoltaic plant is expected to supply more than 100,000 homes and avoid about 57,000 tons of CO2 emissions annually. The company equates that to removing more than 12,000 internal combustion vehicles from the road.

World's Tallest Concrete-Faced Gravel Dam Starts Power Generation

Image
World's Tallest Concrete-Faced Gravel Dam Starts Power Generation

Beijing – October 12, 2026 -- The first two generator units of China's Dashixia Water Control Project in the Tianshan Mountains, Xinjiang, connected to the power grid on September 29 and began generating electricity, marking the project's official operation.

247-meter dam sets height record for its type

The project's concrete-faced sand-gravel dam stands 247 meters high. It is the tallest of its kind among both completed and under-construction dams worldwide. China Energy Engineering Group invested in and built the project.

Completed project to serve 600,000 households and 453,333 hectares of farmland

Once complete, Dashixia will meet the electricity demand of about 600,000 households. It will deliver 3.42 billion cubic meters of ecological water annually to the Tarim River in Xinjiang.

National Grid Completes Thames Tunnel Drive 49 Days Early

Image
National Grid Completes Thames Tunnel Drive 49 Days Early

Tilbury – October 11, 2026 -- National Grid's tunnel boring machine (TBM) Caroline completed a 2.2km drive beneath the River Thames 49 days ahead of the original programme, ending the tunnelling phase of the Grain to Tilbury project, part of The Great Grid Upgrade.

The breakthrough came on Sunday 27 September. Caroline excavated a new high-voltage electricity cable tunnel between Tilbury in Essex and Gravesend in Kent.

Caroline installs more than 10,000 segments across nearly 1,700 rings

The tunnel lining consists of more than 10,000 concrete segments assembled into nearly 1,700 tunnel rings. In her most productive month, Caroline advanced 926 metres and installed 712 lining rings. Peak weekly progress reached 229 metres, and the best single day delivered 41 metres of excavation and 31 installed rings in 24 hours.