Allentown, Pa. – September 17, 2026 -- PPL Electric Utilities has filed a proposal with the Pennsylvania Public Utility Commission to create a new billing mechanism that would directly assign certain transmission network upgrade costs tied to large energy users, including data centers, to those specific customers rather than spreading them across its 1.5 million residential and business accounts.
New rider replaces existing transmission charge without adding fees
The proposed Customer Protection Transmission Rider (CPTR) would replace the utility's current Transmission Service Charge (TSC). PPL Electric says the change does not introduce a new charge but instead restructures how transmission costs are recovered, making them visible as a dedicated line item on customer bills rather than embedded within supply charges.